Balanced Engineering & Construction (BEC) is proud to announce the successful completion of the windshield slide for the Masinloc Unit 5 Environmental Compliance Chimney project in the Philippines.
The project team achieved peak construction progress of 4.0 metres per day, reflecting disciplined execution, rigorous quality control, and highly coordinated site operations.
Delivering complex vertical construction works on schedule requires a combination of engineering precision, productivity management, and strict safety measures. This milestone was delivered on schedule and without incident, reinforcing BEC’s commitment to safety, quality, and performance.
This achievement reflects the team’s disciplined execution, rigorous quality control processes, and strict safety controls for working at height, under the steady leadership of Project Manager Jojo Navarro, whose leadership was instrumental in driving productivity and maintaining programme performance.
BEC extends its appreciation to the entire project team for their professionalism and dedication, and to our client for their continued trust and recognition.
About the Project
The Masinloc Environmental Compliance Chimney forms part of the Masinloc Power Plant Expansion Project in Zambales, Philippines.
BEC was commissioned to design and build the 155-metre single-flue environmental compliance chimney, a critical component supporting plant operations.
The scope of work includes:
- Detailed design and engineering
- Slipform construction of the reinforced concrete windshield
- Fabrication and installation of internal steelwork and access systems
- Installation of flue liner and corrosion protection systems
- Roof structure and ventilation components
- Supply and installation of rack and pinion access hoist
- Mechanical and electrical systems
- Full project management, quality assurance, and safety compliance