BEC Advances Emission Control at Taichung Power Plant

tow hexagonal shaped emission control structures at twilight at Taichung Power Plant

We are proud to announce a significant milestone in our ongoing project at the Taichung Power Plant in Taiwan, where two towering hexagonal emission control structures are reshaping the skyline of one of Asia’s largest power generation units. The focus is currently on the installation of the transition section at Unit 1—a critical elbow component […]

Taichung Reaches 50% Milestone in Slipforming

BEC has reached a significant construction milestone on its ongoing energy infrastructure project in Taichung, Taiwan. The team has successfully completed 50% of the windshield slipforming for the second 150-meter hexagonal chimney, which forms part of the 2 × 1300 MW Taichung Combined Cycle Power Plant. Key project statistics at this stage include: 75 meters […]