Balanced Engineering & Construction (BEC) undertook specialist design and construction works for the Masinloc Unit 5 power plant chimney in Zambales, Philippines, as part of the facility’s generating capacity expansion.
The project involved construction of a reinforced concrete windshield approximately 151 metres high, with an internal diameter of 11 metres, housing a single 5.4-metre-diameter steel flue extending to 155 metres.
BEC’s scope combined detailed engineering, slipform construction, structural steel fabrication, heavy lifting and installation of internal access and mechanical systems.
The reinforced concrete windshield required approximately 2,760 m³ of concrete. Slipform construction progressed at an average rate of 3 metres per day, reaching a peak of 5 metres in a 24-hour period.



The project presented several technical and logistical challenges, requiring precise installation, carefully coordinated lifting operations and effective construction sequencing. BEC worked closely with site teams and engineering designers to address these challenges while maintaining progress against key project milestones.
Precision Steelwork Installation: Accurate positioning and levelling of embedded plates and structural connections were essential to ensure proper alignment of the internal platforms and staircases.
Restricted-Space Flue Installation: Installing the large steel inlet elbow within limited clearances required carefully controlled lifting and positioning to avoid interference with the surrounding structure.
Programme Constraints: Delayed structural handover compressed the construction programme, requiring careful sequencing, resource coordination and close management of critical milestones.
BEC’s design-and-build scope brought together specialist construction methods, steel fabrication and coordinated installation of the chimney’s internal systems.
Key works included:
Masinloc Unit 5 demonstrates BEC’s ability to integrate specialist slipform construction, engineering coordination, structural steel fabrication and heavy lifting within a complex industrial project.
The team achieved an average slipform climbing rate of 3 metres per day, reaching 5 metres in 24 hours, while coordinating concrete placement, reinforcement, embedded steelwork and lifting activities.
Through careful construction sequencing, responsive engineering coordination and close site supervision, BEC progressed critical works and achieved the windshield completion milestone despite programme constraints.
The project reinforces BEC’s capabilities in delivering high-rise industrial structures and integrated chimney construction solutions for the power generation sector.
Looking for a trusted engineering partner for your next industrial or energy infrastructure project? Contact our Engineering team to discuss custom design, construction, and maintenance options.
Masinloc Power Co Ltd
Formosa Heavy Industries (FHI)
Philippines
November, 2026
+(65) 6778 6858
sales@be-con.com