Specialist Slipform Construction of Environmental Compliance Chimney

Case Study

Specialist Slipform Construction of Environmental Compliance Chimney

Balanced Engineering & Construction (BEC) undertook specialist design and construction works for the Masinloc Unit 5 power plant chimney in Zambales, Philippines, as part of the facility’s generating capacity expansion.

The project involved construction of a reinforced concrete windshield approximately 151 metres high, with an internal diameter of 11 metres, housing a single 5.4-metre-diameter steel flue extending to 155 metres.

BEC’s scope combined detailed engineering, slipform construction, structural steel fabrication, heavy lifting and installation of internal access and mechanical systems.

The reinforced concrete windshield required approximately 2,760 m³ of concrete. Slipform construction progressed at an average rate of 3 metres per day, reaching a peak of 5 metres in a 24-hour period.

Challenges

The project presented several technical and logistical challenges, requiring precise installation, carefully coordinated lifting operations and effective construction sequencing. BEC worked closely with site teams and engineering designers to address these challenges while maintaining progress against key project milestones.

Precision Steelwork Installation:  Accurate positioning and levelling of embedded plates and structural connections were essential to ensure proper alignment of the internal platforms and staircases.

Restricted-Space Flue Installation: Installing the large steel inlet elbow within limited clearances required carefully controlled lifting and positioning to avoid interference with the surrounding structure.

Programme Constraints: Delayed structural handover compressed the construction programme, requiring careful sequencing, resource coordination and close management of critical milestones.

BEC's approach

BEC’s design-and-build scope brought together specialist construction methods, steel fabrication and coordinated installation of the chimney’s internal systems.

Key works included:

  • Detailed design, engineering and slipform construction of the reinforced concrete windshield.
  • Fabrication and installation of internal structural steelwork, steel flue liner cans and associated components.
  • Heavy lifting and positioning of steel components, including the inlet elbow within restricted installation clearances.
  • Installation of internal access platforms, staircases and liner support systems.
  • Supply and installation of the rack-and-pinion access hoist.
  • Installation of corrosion protection, roof and ventilation components.
  • Electrical works, including access lighting, lightning protection and aviation warning lights.
  • Project supervision, quality assurance and safety management throughout construction.

The BEC Advantage

Masinloc Unit 5 demonstrates BEC’s ability to integrate specialist slipform construction, engineering coordination, structural steel fabrication and heavy lifting within a complex industrial project.

The team achieved an average slipform climbing rate of 3 metres per day, reaching 5 metres in 24 hours, while coordinating concrete placement, reinforcement, embedded steelwork and lifting activities.

Through careful construction sequencing, responsive engineering coordination and close site supervision, BEC progressed critical works and achieved the windshield completion milestone despite programme constraints.

The project reinforces BEC’s capabilities in delivering high-rise industrial structures and integrated chimney construction solutions for the power generation sector.

Looking for a trusted engineering partner for your next industrial or energy infrastructure project? Contact our Engineering team to discuss custom design, construction, and maintenance options.

Explore more slipformed chimney projects

Projects Details:
Owner

Masinloc Power Co Ltd

Client

Formosa Heavy Industries (FHI)

Location

Philippines

Completed

November, 2026